AltaLink projects underway will ensure reliable electricity supply

Ensuring electricity is supplied in a reliable and non-interruptive manner is the aim of AltaLink projects underway

Ensuring electricity is supplied in a reliable and non-interruptive manner is the aim of AltaLink projects underway in and around the Sylvan Lake and Eckville area.

An existing substation near Eckville built about 50 years ago is being relocated, and its aging equipment replaced.

Such changes will “maintain the reliability of the system in the area”, according to Peter Brodsky, manager of external communications.

The new substation will be situated about 30 metres to the north of the current location, he added.

The new location was determined after feedback from residents indicated a desire to see it moved farther away.

Attempts to meet their request were made unsuccessfully.

“We did receive feedback from residents in the area about the possibility of moving it approximately 100 metres to accommodate some municipal development,” said Brodsky.

After it was determined that the substation could be moved a maximum distance of 87 metres, an amendment to the facility application was filed requesting permission from Alberta Utilities Commission (AUC) to do so.

“Unfortunately, they did not approve that request, and put us back to the 30 metres we were originally looking at,” said Brodsky.

He explained that the 30-metre move was initially considered by AltaLink as it had “the lowest potential for environmental impacts”.

“Although we did amend our proposal based on the request of landowners in the area, we do believe the 30-metre move is still the best one all around.”

The application was approved in October, with construction expected to begin in March of next year. Energization is expected by January 2015.

A July 2012 letter addressed to stakeholders noted that new equipment will include a circuit breaker, a switchgear building, a control building and a transformer with built-in regulator.

The letter also noted the potential signs of work on the project, including noise and the presence of construction crews.

Another project — Red Deer Area Transmission Development — has also seen upgrades made in the area.

Upgrade of the Benalto substation, which is now energized, was one of several substation upgrades made recently in the Red Deer and Sylvan Lake area as part of the project’s first stage.

Its second stage will see about 75 kilometres of existing area transmission lines rebuilt.

Although that application is currently before the AUC, construction could begin within months, according to Brodsky.

“Our hope would be that construction could begin in June 2014, with the belief that we would be done by August 2015.

That tentative schedule, however, is dependent upon the AUC, he added.

He also noted that all transmission line work will be carried out in existing road allowances and previously disturbed land.

Collecting and acknowledging stakeholders’ feedback is key to ensuring their concerns are addressed by AltaLink.

With the Benalto substation, concerns about visual impacts of the project were addressed by an AltaLink commitment to planting tree screens around it, and in “areas where it makes sense to minimize the visual disturbance that may be of concern”, according to Brodsky.

Noise levels, another concern for many, comply with AUC Rule 012 – Noise Control.

“We’re very careful to make sure that we respect that,” said Brodsky.

Information about both projects, including maps, is available on AltaLink’s website at www.altalink.ca.

 

Just Posted

Sylvan Lake RCMP search for two missing women

Serenity Rosewell and Jazmine Sleva were reported missing by their families

Accused Jason Klaus testifies in triple-homicide trial in Red Deer

Klaus charged with three counts of first-degree murder, one count of arson

Christmas Bureau receives large cheque

Big Bear Energy donates to their community

The Giving Tree is back

Friends of Bethany encourage community to give the gift of time and gifts for Christmas

Preparation for holiday pageant is underway

H.J. Cody needs support for drama performance

BC RCMP hunt for white SUV that rammed cruiser

Kamloops RCMP are looking for a white SUV headed north on the Yellowhead Highway

Tourism numbers continue to climb in B.C.

The biggest rise in international travellers to British Columbia are those coming from Australia

Canadian screen stars want ‘action’ from industry meeting on sexual misconduct

‘Of course there’s been sexual harassment here. Absolutely. No question.’

Opioid prescriptions up across Canada: report

The report shows the number of opioid prescriptions rose by almost seven per cent, while daily doses on average dropped

Russian meddling has implications for Canada

Kosovo president Hashim Thaci warns that Russian meddling has implications for Canada

Health Canada hints at government’s plans for legal pot

Health warnings, plain covers for pot packs under proposed regulations

Washington governor tells BC don’t be ‘daunted’ by Trump

“I want to assure this assembly that no matter who is in the White House, it won’t affect Washington state’s relationship with Canada or British Columbia.”

Feds plan to spend billions on housing strategy

However much of the $15.9 billion will not be spent until after the next election in 2019

Most Read