Four new storage tanks have been constructed at Trans Mountain’s Edmonton terminal to prepare for opening of the oil pipeline expansion from Alberta to Westridge Terminal in Burnaby B.C. (Trans Mountain)

Trans Mountain begins laying Alberta pipeline for expansion

Construction continues at Westridge terminal in Burnaby B.C.

Trans Mountain Corp. has begun laying pipe across the Alberta segment of its oil pipeline twinning project, expecting to have the first pipe welded, tested and buried by Christmas.

Construction so far has included completion of four new storage tanks at the federal government-owned company’s Edmonton Terminal, and continued work on the Westridge Terminal facilities at Burnaby to accommodate additional tankers for exporting crude.

Pipe is being assembled on the Greater Edmonton section, with clearing, grading, utility relocation and worksite preparations for a series of tunnel-bored sections. Horizontal drilling is planned for 13 sections on the Alberta side of the project, to cross watercourses, railways, major roads, sensitive environmental areas and urban areas, Trans Mountain said in its latest project update.

Trenchless construction is also expected to play a large role in the B.C. section of the project, where thousands of property owners have moved in along the right-of-way since the original Trans Mountain was built in 1954.

Trenchless construction is also expected to play a large role in the B.C. section of the project, where thousands of property owners have moved in along the right-of-way since the original Trans Mountain was built in 1954 to supply refineries at Burnaby and Washington state as well as tanker exports from Burnaby.

RELATED: CEO promises ‘the best darn pipeline in the world’

RELATED: Indigenous leaders choose pipelines over poverty

RELATED: Oil-by-rail traffic rises as B.C. battles Trans Mountain

The B.C. government has continued to oppose the Trans Mountain expansion, supported by Washington Gov. Jay Inslee, despite increased crude by rail coming through Alberta and B.C. to Washington since the existing Trans Mountain line became over-subscribed.

In a year-end interview with Black Press, B.C. Premier John Horgan acknowledged that construction is likely to intensify an already acute shortage of skilled construction workers, as work camps and gas pipeline spreads take shape across northern B.C. to supply the LNG Canada project from Dawson Creek to Kitimat.

B.C. is using a union-only construction model to build the Kicking Horse Pass and other sections of the Trans-Canada Highway from Kamloops to the Alberta border, as well as replacing the Pattullo Bridge and building the Broadway subway line in Metro Vancouver. A skilled labour shortage is driving up costs on those projects, Horgan said.

“And at the same time we have private sector projects like LNG Canada, and potentially the Trans Mountain pipeline, that are going to be taking a whole bunch of workers out of play when it comes to public contracts, and that’s a challenge for government,” Horgan said.

From the Greater Edmonton section, the Trans Mountain right of way goes to Edson, Hinton, Spruce Grove, Stony Plain and Wabamun before reaching the Jasper-Mount Robson stretch where twinning was done a decade ago.

Entering B.C. in the North Thompson region, the pipeline route goes by Avola, Barriere, Blue River, Clearwater, Valemount and Vavenby, where the forest industry has been wound down due to market conditions and loss of lumber to beetle infestations and fires.

At West Barriere, another existing expansion section will be tested and activated, running from a pump station north of Barriere to a new Black Pines pump station north of Kamloops. From there the project goes past Kamloops and Merritt, then down the Coquihalla Pass to Hope.

The project proceeds down theFraser Valley through Chilliwack, Abbotsford and Langley, then into the heavily populated Lower Mainland through Langley, Surrey, Coquitlam and Burnaby.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureTrans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

There were 410 COVID-19 cases recorded in Alberta Wednesday. (File photo)
Alberta records 410 new COVID-19 cases Wednesday

Central zone dropped to 160 active cases

Shaun Isaac, owner of Woodchucker Firewood in Trochu, is awaiting a new shipment during a firewood shortage in the province. All of the wood he has left is being saved for long-time customers who need it to heat their homes. (Contributed photo).
Firewood shortage in central Alberta caused by rising demand, gaps in supply

‘I’ve said “No” to more people than ever’: firewood seller

Sharon Hickin, general manager of the Days Inn Sylvan Lake and the new Lake House Diner, poses for a photo outside the new restaurant. Photo by Megan Roth/Sylvan Lake News
Pandemic puts extra hurdles in place for new Sylvan Lake businesses

Over the past seven months numerous new businesses have opened in Sylvan Lake, despite the pandemic

Sylvan Lake Wranglers. File Photo
Sylvan Lake Wranglers ready for shorten hockey season

The HJHL will have a 20 game season, playing four games in a cohort and then going dark for 14 days

Royal Alexandra Hospital front-line workers walk a picket line after walking off the job in a wildcat strike in Edmonton, on Monday, October 26, 2020. THE CANADIAN PRESS/Jason Franson
Alberta labour board orders health-care staff who walked off the job to go back to work

Finance Minister Travis Toews said in a news release that he was pleased with the labour board’s decision

Husky Energy logo is shown at the company’s annual meeting in Calgary on May 5, 2017. THE CANADIAN PRESS/Jeff McIntosh
Husky pipeline spills 900,000 litres of produced water in northwestern Alberta

The energy regulator says environmental contractors are at the site

A raccoon paid a visit to a Toronto Tim Hortons on Oct. 22, 2020. (shecallsmedrew/Twitter)
Who are you calling a trash panda? Raccoon takes a shift at Toronto Tim Hortons

Tim Hortons said animal control was called as soon they saw the surprise visitor

file photo
Maskwacis RCMP investigate pedestrian fatality

Collision on Highway 2A causing fatality still under investigation.

Rachel Notley, leader of Alberta’s official Opposition, speaks in Edmonton on Wednesday, Oct. 16, 2019. Notley says the government needs to sharply ramp up the number of contact tracers if it wants to get a handle on the rising number of COVID-19 cases. THE CANADIAN PRESS/Jason Franson
Alberta Opposition calls for more COVID-19 contact tracers as case numbers rise

Alberta has about 800 tracers, and chief medical health officer Dr. Hinshaw says more are being recruited

Royal Alexandra Hospital front-line workers walk a picket line after walking off the job in a wildcat strike in Edmonton, on Monday, October 26, 2020. Hospital and health-care workers who staged a one-day illegal walkout returned to work Tuesday while politicians swapped recriminations and accusations in the house over the dispute. THE CANADIAN PRESS/Jason Franson
Alberta health staff return to work, surgeries resume after one-day walkout

AHS estimated 157 non-emergency surgeries, most of them in Edmonton, had to be postponed as a result of the walkout

Prime Minister Justin Trudeau makes his way to provide an update on the COVID pandemic in Ottawa on Tuesday, Oct. 27, 2020. Canada has reached a grim milestone in the COVID-19 pandemic, surpassing 10,000 novel coronavirus deaths. THE CANADIAN PRESS/Sean Kilpatrick
Alberta COVID deaths pushes Canada past milestone of 10,000 deaths

Canada crossed the threshold of 5,000 deaths on May 12, a little over two months after the first was reported

Cases in Ponoka (East Ponoka County) as of Oct. 27. (alberta.ca)
Diagnosed cases of COVID-19 at three Ponoka businesses

Town ‘strongly encouraging’ residents to wear non-medical masks in public

Most Read