AltaLink projects underway will ensure reliable electricity supply

Ensuring electricity is supplied in a reliable and non-interruptive manner is the aim of AltaLink projects underway

Ensuring electricity is supplied in a reliable and non-interruptive manner is the aim of AltaLink projects underway in and around the Sylvan Lake and Eckville area.

An existing substation near Eckville built about 50 years ago is being relocated, and its aging equipment replaced.

Such changes will “maintain the reliability of the system in the area”, according to Peter Brodsky, manager of external communications.

The new substation will be situated about 30 metres to the north of the current location, he added.

The new location was determined after feedback from residents indicated a desire to see it moved farther away.

Attempts to meet their request were made unsuccessfully.

“We did receive feedback from residents in the area about the possibility of moving it approximately 100 metres to accommodate some municipal development,” said Brodsky.

After it was determined that the substation could be moved a maximum distance of 87 metres, an amendment to the facility application was filed requesting permission from Alberta Utilities Commission (AUC) to do so.

“Unfortunately, they did not approve that request, and put us back to the 30 metres we were originally looking at,” said Brodsky.

He explained that the 30-metre move was initially considered by AltaLink as it had “the lowest potential for environmental impacts”.

“Although we did amend our proposal based on the request of landowners in the area, we do believe the 30-metre move is still the best one all around.”

The application was approved in October, with construction expected to begin in March of next year. Energization is expected by January 2015.

A July 2012 letter addressed to stakeholders noted that new equipment will include a circuit breaker, a switchgear building, a control building and a transformer with built-in regulator.

The letter also noted the potential signs of work on the project, including noise and the presence of construction crews.

Another project — Red Deer Area Transmission Development — has also seen upgrades made in the area.

Upgrade of the Benalto substation, which is now energized, was one of several substation upgrades made recently in the Red Deer and Sylvan Lake area as part of the project’s first stage.

Its second stage will see about 75 kilometres of existing area transmission lines rebuilt.

Although that application is currently before the AUC, construction could begin within months, according to Brodsky.

“Our hope would be that construction could begin in June 2014, with the belief that we would be done by August 2015.

That tentative schedule, however, is dependent upon the AUC, he added.

He also noted that all transmission line work will be carried out in existing road allowances and previously disturbed land.

Collecting and acknowledging stakeholders’ feedback is key to ensuring their concerns are addressed by AltaLink.

With the Benalto substation, concerns about visual impacts of the project were addressed by an AltaLink commitment to planting tree screens around it, and in “areas where it makes sense to minimize the visual disturbance that may be of concern”, according to Brodsky.

Noise levels, another concern for many, comply with AUC Rule 012 – Noise Control.

“We’re very careful to make sure that we respect that,” said Brodsky.

Information about both projects, including maps, is available on AltaLink’s website at www.altalink.ca.

 

Just Posted

Drew Persson national champion in Greco wrestling

Persson placed first in the Greco category at the national championship

Pigeon Lake Lions organize pop can tab collection

Sylvan Lake, Rimbey, Winfield also collected tabs

Gymnast Madison Ruff joins Team Alberta

Ruff will compete in trampoline and tumbling at the national gymnastics championship this July

Pigeon Lake Lions organize pop can tab collection

Sylvan Lake, Rimbey, Winfield also collected tabs

PHOTO: Family Doctor Day declared

Dr Fred Janke was present for the declaration of Family Doctor Day

SLIDESHOW: The summer season kicks off with the Farmer’s Market

The first weekly farmer’s market was held on May 18

Pipeline more important than premiers meeting: Notley

“Canada has to work for all Canadians, that’s why we’re fighting for the pipeline”

Canadian government spending tens of millions on Facebook ads

From January 2016 to March 2018, feds spent more than $24.4 million on Facebook and Instagram ads

B.C. sues Alberta over bill that could ‘turn oil taps off’

Lawsuit is the latest move in the two provinces’ ongoing feud over the Kinder Morgan pipeline

Liberal government introduces measures to update Canada’s family laws

Justice officials say there have not been substantial updates to federal family laws in 20 years

Teen must repay $37M for starting Oregon wildfire

A teenager who started a major wildfire in Oregon has been ordered to pay restitution

Canada’s G7 goal on development: luring private capital to poor nations

G7 finance and international development ministers convene in British Columbia next week

Congressional leaders to review information on Russia probe

Trump said he will “demand” that the Justice Department open an investigation into whether the FBI infiltrated his presidential campaign

Canadians stranded in Cuba after plane crash returning home

Montreal-based travel agency says hundreds of Canadians who were stuck in Cuba since a plane crash last week are returning home

Most Read